Moving-in steps

BER will begin operations on October 31. The Supervisory Board approved this proposal by the management at its meeting on November 29, 2019. A week later, on November 8, 2020, scheduled flight operations will end at Tegel. In between there are three major steps in which all flight operations will move from Tegel Airport to BER.

Step 1

Commissioning BER
31 October 2020

Step 2

Commissioning of the South Runway
04 November 2020

Step 3

Closure of Tegel
08 November 2020